WORKDAY Function in Microsoft Excel: Syntax, Examples & Compatibility

Date & Time Beginner Microsoft Excel

Learn how to find a due date a set number of working days after an initial date in Microsoft Excel. Includes syntax, two verified-by-reasoning results, troubleshooting and portability notes.

Verification status: See the evidence and test scope described in this guide. How formula examples are checked

Quick answer: WORKDAY returns a date a specified number of working days before or after a start date. The standard calendar excludes Saturday, Sunday and the supplied holiday dates. Positive offsets move forward; negative offsets move backward.

Availability and version history

  • Introduced: Introduction version not established by the official history reviewed.
  • Availability: Official help lists Excel for Microsoft 365, Excel for Microsoft 365 for Mac, Excel 2024, Excel 2024 for Mac, Excel 2021, Excel 2021 for Mac, Excel 2019, Excel 2016.
  • Checked: October 14, 2026; official WORKDAY reference. Documentation check, not a new native test; existing example-verification notes retain their scope.

Syntax and input setup

=WORKDAY(start_date, days, [holidays])

Examples use English function names and comma separators. Enter formula inputs exactly as shown, keep outputs outside the input cells, and use the specified date or numeric output format.

The start date and day offset are required. Holidays is an optional range of actual dates, or an array of date serial numbers. It is not a list of holiday names, and Excel does not automatically obtain local holidays for this argument.

Format the result as a date. The underlying result is a date serial, unlike NETWORKDAYS, which returns a count. Square brackets indicate an optional argument and are not typed.

Two original worked controls

=TEXT(WORKDAY(DATE(2026,6,1),4),"yyyy-mm-dd")
=TEXT(WORKDAY(DATE(2026,6,1),-1),"yyyy-mm-dd")

Expected results are 2026-06-05 and 2026-05-29. June 1, 2026 is Monday. Moving forward four working days visits Tuesday through Friday; moving backward one reaches the preceding Friday. These TEXT wrappers make the displayed check unambiguous but return text, not reusable numeric dates.

For further date arithmetic use the inner WORKDAY result and apply a date format instead. A cell that visually resembles a date does not necessarily have the same stored type as the numeric result.

Example: supply the complete holiday range

On a separate sheet put =DATE(2026,6,3) in H2 and =DATE(2026,6,5) in H3. These are a Wednesday and Friday excluded by this example’s calendar; they are not asserted to be public holidays anywhere.

=WORKDAY(DATE(2026,6,1),4,$H$2:$H$3)

Expected date: June 9, 2026. The four counted dates are June 2, June 4, June 8 and June 9. Both holidays and the weekend are skipped. Supplying H2 alone would omit the Friday exclusion and instead finish on June 8.

Absolute references keep the holiday list fixed when a schedule is filled down. Check that every holiday cell contains a valid date and that the intended list has not been cut short.

Advanced example: generate a milestone schedule

Put offsets 1, 2, 3 and 4 in A2:A5 and =DATE(2026,6,1) in F2. Keep the two holidays in H2:H3 above. Enter in B2 and fill down:

=WORKDAY($F$2,A2,$H$2:$H$3)

Expected dates are June 2, June 4, June 8 and June 9, 2026. Every milestone is measured from the same fixed start. Filling a relative start reference down would create a different calculation, even if the first row looked right.

These offsets count working dates, not hours of effort. Four eight-hour shifts are a scheduling assumption outside the function; WORKDAY does not allocate staff or track partial-day availability.

Advanced example: move backward through the same calendar

=WORKDAY(DATE(2026,6,8),-2,$H$2:$H$3)

Expected date: June 2, 2026. Going backward skips Sunday and Saturday, then the June 5 holiday. June 4 is the first counted working date, June 3 is excluded, and June 2 is the second.

Simply subtracting two calendar days from June 8 gives June 6, a Saturday. A negative WORKDAY offset is therefore not interchangeable with ordinary date subtraction.

Noninteger offsets and weekend starts

Microsoft explicitly truncates a noninteger days argument. With the two-holiday calendar, an offset of 4.9 from June 1 has the same expected date as 4: June 9. With no holidays, −1.9 from June 1 is truncated toward zero to −1 and gives May 29.

For a Saturday start, =WORKDAY(DATE(2026,6,6),1) has expected date June 8, and the corresponding −1 offset gives June 5. These positive and negative controls count working dates strictly after or before the supplied start.

Zero offsets on nonworking starts, fractional holiday entries and every duplicate/blank holiday-list case are outside the tested documentation model here. Do not silently normalize those inputs using a rule copied from another product.

Advanced check: reconcile a due date with a count

For June 1 through June 9 using H2:H3, NETWORKDAYS has expected count 5: June 1, 2, 4, 8 and 9. WORKDAY used offset 4 because it moved four working dates after a starting date that was itself working.

The relationship is useful for this validated calendar and working start; it is not permission to subtract one from every workday count regardless of weekend or holiday endpoints. State whether the start belongs to the business measure.

Errors and calendar choices

Microsoft documents #VALUE! for an invalid date argument and #NUM! if the requested movement produces an invalid result date. Its broad date-error wording should not be read as requiring the days offset itself to be a calendar date; days is a numeric count.

For a different recurring weekend, the vendor points to WORKDAY.INTL. Do not mark Saturdays as normal working days merely by leaving them out of the holiday list: the standard weekend exclusion still applies. No alternate-weekend formula is certified by this guide.

DATE in Microsoft Excel | DATE in Google Sheets | WEEKDAY in Microsoft Excel | WEEKDAY in Google Sheets | editorial testing standards

The full manuscript and original worked formulas were reviewed on October 14, 2026. The approved availability/history section is unchanged. Expected results are independently calculated date/arithmetic models or explicitly documented rules, not native Excel output. Current-clock formulas have conditional rather than fixed outputs. Client-specific time-zone, mixed-type and boundary behavior is not inferred from another spreadsheet.