BINOM.DIST in WPS Spreadsheet: Calculate Exact and Cumulative Probabilities
Use BINOM.DIST and BINOMDIST for exact, at-most and at-least probabilities, with independent numeric checks.
Verification status: See the evidence and test scope described in this guide. How formula examples are checked
Quick answer: BINOM.DIST calculates probabilities for a fixed number of independent success/failure trials with the same success probability on every trial. =BINOM.DIST(8,10,0.5,FALSE) has the independently calculated expectation 0.0439453125, the probability of exactly eight successes in ten fair trials. Use TRUE for at most eight successes instead.
Availability and evidence scope
The official WPS BINOM.DIST lesson documents this function for WPS Office for Windows Personal. The source was checked on October 19, 2026. It does not establish the first release, the last supported release, or an exact installed build. Availability in Mac, Linux, web, mobile and other editions remains unverified.
Examples below distinguish documented behavior from independently calculated controls. No results were captured from a new WPS execution for this guide. No native screenshot or cross-client compatibility test is claimed.
Syntax and arguments
=BINOM.DIST(number_s,trials,probability_s,cumulative)
=BINOMDIST(number_s,trials,probability_s,cumulative)
| Argument | Required? | Meaning |
|---|---|---|
number_s |
Yes | Number of successes, from zero through the number of trials. |
trials |
Yes | Fixed number of independent trials. |
probability_s |
Yes | Per-trial success probability, from 0 to 1. |
cumulative |
Yes | FALSE for exactly number_s; TRUE for zero through number_s. |
There is no documented default for cumulative; supply it explicitly. Enter 50% or 0.5 for a fifty-percent probability, not 50. The official lesson says the two count arguments, number_s and trials, are truncated to integers. That rule does not turn 0.5 into zero: probability_s remains a probability.
Although the translated WPS lesson uses “probability density” for FALSE, this discrete result is a probability mass at an integer count. It is not a continuous density or a cumulative percentage by default.
BINOMDIST belongs to the same documented family
The official BINOMDIST lesson calls BINOM.DIST its newer function and says the usage is the same. Both names therefore belong in this guide. This does not establish an introduction version, a removal date, or that BINOMDIST has been retired.
For the example above, =BINOMDIST(8,10,0.5,FALSE) has the same independent expected probability, 0.0439453125. Keep the spelling required by a workbook’s target installation and test it there; a documentation relationship is not a native compatibility test.
Example 1: exactly eight successes
Enter this input block:
| Cell | Label | Value |
|---|---|---|
| B1 | Successes | 8 |
| B2 | Trials | 10 |
| B3 | Success probability | 0.5 |
| B4 | Cumulative? | FALSE |
=BINOM.DIST(B1,B2,B3,B4)
Expected result: 0.0439453125, or 4.39453125% with percentage formatting. The WPS lesson uses the same ten-trial, eight-success, 0.5-probability setup; the decimal here is independently calculated, not transcribed from a native result.
The arithmetic is 45 possible placements of the eight successes, each with probability 0.5 raised to the tenth power: 45/1024. This provides a small, exact check on both the function arguments and the percentage display.
Example 2: distinguish exactly, at most and at least
| Question | Formula | Independent expected probability |
|---|---|---|
| Exactly 8 of 10 | =BINOM.DIST(8,10,0.5,FALSE) |
0.0439453125 |
| At most 8 of 10 | =BINOM.DIST(8,10,0.5,TRUE) |
0.9892578125 |
| At least 8 of 10 | =1-BINOM.DIST(7,10,0.5,TRUE) |
0.0546875 |
The last formula subtracts the probability of 0 through 7, leaving 8, 9 and 10. Subtracting the cumulative probability at 8 would answer “more than 8,” excluding exactly eight. This one-count difference is a common source of incorrect risk estimates.
A check for the last result is (45+10+1)/1024 = 0.0546875, adding the three permitted success counts. Formatting the answer as a percentage changes its display, not the underlying probability.
Advanced example: inspect a batch-acceptance rule
Suppose a theoretical quality model has 20 independently inspected items, each with a fixed defect probability of 0.10. Treat “defective” as the counted success event. A rule accepts a batch if at most two defects are found.
| Cell | Meaning | Value |
|---|---|---|
| E1 | Number inspected | 20 |
| E2 | Defect probability | 0.10 |
| E3 | Maximum accepted defects | 2 |
=BINOM.DIST(E3,E1,E2,TRUE)
The independent expected acceptance probability is approximately 0.6769268052 (67.69268052%). For more than two defects:
=1-BINOM.DIST(E3,E1,E2,TRUE)
The expected rejection probability is approximately 0.3230731948. Their sum should be 1 apart from displayed rounding. The calculation is conditional on the model’s assumptions; it does not establish the real defect rate or prove that a sampling policy is suitable.
Independence and a constant probability matter. Items affected by one shared production fault may not be independent. Sampling without replacement from a small, fixed lot can change the probability after each draw. In either situation, investigate the model rather than adjusting the cumulative switch until a preferred answer appears.
Errors, limits and troubleshooting
#VALUE!: WPS documents this for nonnumericnumber_s,trialsorprobability_s. Check imported text before interpreting the result.#NUM!: documented when successes are below zero or above trials, or probability is outside 0–1.- Unexpectedly large probability: check whether TRUE was used for a question asking “exactly.”
- Unexpectedly small probability: check whether FALSE was used for “at most,” or whether a displayed percentage was entered as a whole number.
- Fractional counts: the documented truncation is not a sensible way to express half an inspection. Validate whole-number counts before calculation.
- Very small tail probability: subtracting a cumulative value close to one can make numerical precision important. The independent checks here use modest inputs; no large-count accuracy bound is established.
ISNUMBER can help identify numeric inputs, but it does not verify the permitted ranges or the independence assumptions. Keep those checks separate. Do not hide an unexpected error with an unexplained zero: zero is itself a meaningful probability.
References and verification
- Official WPS BINOM.DIST lesson (Chinese; Windows Personal documentation).
- Official WPS BINOMDIST lesson, establishing the documented naming relationship.
The documentation establishes the syntax and stated behavior. Original examples were checked independently under the assumptions stated alongside them; target-build execution remains a separate check. Version boundaries have not been inferred from another spreadsheet product.